Project Management Professional (PMP) Exam Practice – Question1810

On your systems development project, you noted during a review that the system had less functionality than planned at the critical design review. This note suggests that during the control risks process you used which following tools and techniques?


A.
Risk reassessment
B. Variance analysis
C. Technical performance measurement
D. Reserve analysis

Correct Answer: C

Explanation:

Explanation:
Technical performance measurement compares technical accomplishments to date to the project plan’s schedule of technical achievement. Deviation, such as less functionality than planned at a key milestone, can help to forecast the degree of success in
achieving the project scope.