Project Management Professional (PMP) Exam Practice – Question1811

The workaround that you used to deal with a risk that occurred should be documented and included in which following processes?


A.
Report performance and monitor and control risks
B. Validate scope and perform quality assurance
C. Direct and manage project work and perform integrated change control
D. Monitor and control project work and control risks

Correct Answer: D

Explanation:

Explanation:
A workaround is a form of corrective action, as it is a response to a threat that has occurred for which a prior response had not been planned or was not effective.