Project Management Professional (PMP) Exam Practice – Question1812

Contested changes are requested changes when the buyer and seller cannot agree on compensation for the change. They are also known as all but which one of the following?


A.
Disputes
B. Demands
C. Appeals
D. Claims

Correct Answer: B

Explanation:

Explanation:
Claims administration is a tool and technique in the control procurements process. When the buyer and seller cannot agree, this is also called claims, disputes, or appeals and should be documented, processed, monitored, and managed throughout the contract
life cycle.