Project Management Professional (PMP) Exam Practice – Question1813

A structured review of the seller's progress to deliver project scope and quality within cost and schedule is known as a(n)______________


A.
Procurement performance review
B. Procurement audit
C. Inspection
D. Status review meeting

Correct Answer: A

Explanation:

Explanation:
These reviews are a tool and technique of the control procurements process, which can include a review of seller-prepared documentation and buyer inspections. They seek to identify performance successes or failures, progress with respect to the contract
statement of work and contract noncompliance.