Project Management Professional (PMP) Exam Practice – Question1815
The greatest degree of uncertainty is encountered during which phase of the project life cycle?
A. Concept B. Planning C. Implementation D. Closeout
Correct Answer: A
Explanation:
Explanation:
The greatest degree of uncertainty about the future is encountered during the concept phase or at the start of the project. The direction of the project is determined in this phase, and the decisions made have the greatest influence on scope, quality, time, and cost
of the project.