Project Management Professional (PMP) Exam Practice – Question1819

Work completed, key performance indicators, technical performance measures, start and finish dates of schedule activities, number of change requests, number of defects, actual costs, and actual decisions are examples of work performance data are an output
of______________


A.
Project plan development
B. Risk control
C. Monitor and control project work
D. Direct and manage project work

Correct Answer: D

Explanation:

Explanation:
Work performance data containing these examples are an output of direct and manage project work. They are raw observations and measurements identified as activities are being performed to complete the work of the project. These data often are viewed at the
lowest level of detail from which information is derived by other processes. The data then are gathered as the work is done and passed to the controlling processes of the various processes for further analyses.