Work completed, key performance indicators, technical performance measures, start and finish dates of schedule activities, number of change requests, number of defects, actual costs, and actual decisions are examples of work performance data are an output
of______________
A. Project plan development
B. Risk control
C. Monitor and control project work
D. Direct and manage project work