As you use the critical chain method in lieu of the critical path method in developing your schedule, assume you have determined the buffer schedule activities. Your planned activities are scheduled to their latest possible planed start and end dates. Therefore, you
are focusing on______________
A. Managing the free float of each network path
B. Managing the total float of the network paths
C. Managing remaining buffer durations against the remaining durations of task chains
D. Managing the total buffer durations against the durations of the task chains
are focusing on______________
A. Managing the free float of each network path
B. Managing the total float of the network paths
C. Managing remaining buffer durations against the remaining durations of task chains
D. Managing the total buffer durations against the durations of the task chains