Project Management Professional (PMP) Exam Practice – Question1824

Before considering a project closed, what document should be reviewed to ensure that project scope has been satisfied?


A.
Project scope statement
B. Project management plan
C. Project closeout checklists
D. Scope management plan

Correct Answer: B

Explanation:

Explanation:
Project scope is measured against the project management plan. The project scope statement and scope baseline are subsets of the project management plan. However, the whole plan and all the baselines (cost and schedule) need to be met in addition to part
of the scope. The project management plan is the agreement between the project manager and sponsor and defines what constitutes project completion.