Project Management Professional (PMP) Exam Practice – Question1826

All the following elements are organizational process asset updates, resulting from closing a project or phase EXCEPT______________


A.
Project files
B. Project or phase closure documents
C. Historical information
D. Final product, service, or result transition

Correct Answer: D

Explanation:

Explanation:
All the elements are outputs of the close project or phase processes, but the final product, service, or result transition is not part of the organizational process assets. It is an output on its own and involves the product that the project was created to produce.