Project Management Professional (PMP) Exam Practice – Question1829

Validate scope works hand-in-hand with control quality and generally follows control quality. A tool and technique used in validate scope that is not used in control quality is______________


A.
Group decision-making techniques
B. Inspection
C. Statistical sampling
D. Variance analysis

Correct Answer: A

Explanation:

Explanation:
Both processes use inspection. Validate scope also uses group-decision making techniques to reach a conclusion when the validation is performed by the project team and other stakeholders. Methods to reach a group decision include: unanimity, majority,
plurality, and dictatorship.