Project Management Professional (PMP) Exam Practice – Question1830
Research has shown that during the execution phase of the project, the majority of conflicts involve______________
A. Personalities B. Project priorities C. Cost D. Schedule
Correct Answer: D
Explanation:
Explanation:
In a study of sources of conflict by project life-cycle phase, seven different causes of conflict were identified. In the execution phase, the highest-ranking sources of conflict were schedules, technical issues, and personnel, in this order, followed by priorities,
administrative procedures, cost, and personalities.