Improvement to the processes and the product is a goal of project quality management. Assume that after completing a quality audit, you have discovered some gaps/shortcomings in the way that the project team is completing one deliverable. As an output to
perform quality assurance, you would create which following item that feeds directly into the perform integrated change control processes?
A. Quality management plan updates
B. Risk register
C. Change requests
D. Project document updates
perform quality assurance, you would create which following item that feeds directly into the perform integrated change control processes?
A. Quality management plan updates
B. Risk register
C. Change requests
D. Project document updates