The estimate costs process uses all the following tools and techniques EXCEPT______________


A.
Three-point estimating
B. Cost of quality assumptions
C. Reserve analysis (contingency reserves)
D. Basis of estimates

Correct Answer: D

Explanation:

Explanation:
Basis of estimates is an output from the estimate costs process.