Project Management Professional (PMP) Exam Practice – Question1838

A contract typically is used when a project is being performed for an external customer. An agreement is used as an input to______________


A.
Develop project charter
B. Develop project team
C. Plan procurement management
D. Conduct procurements

Correct Answer: A

Explanation:

Explanation:
In the develop project charter process, an agreement is an input to define initial intentions for the project. They may take the form of a type of contract such as memorandums of understanding, service level agreements, letter of agreement, letter of intent, verbal
agreement, or other written agreements.