Project Management Professional (PMP) Exam Practice – Question1839

As you prepare to close your project, which of the following is an input to the close project or phase process?


A.
Work performance information
B. Expert judgment
C. Accepted deliverables
D. Change requests

Correct Answer: C

Explanation:

Explanation:
Accepted deliverables is an input to the close project or phase. The other selections are inputs or tools and techniques for other processes.