Project Management Professional (PMP) Exam Practice – Question1840

Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following components EXCEPT______________


A.
Project scope statement
B. WBS
C. WBS dictionary
D. Scope management plan

Correct Answer: D

Explanation:

Explanation:
The scope management plan is not part of the scope baseline. However, both the scope baseline and the scope management plan are a part of the larger project management plan.