Project Management Professional (PMP) Exam Practice – Question1841

Assume you have been working with your sponsor to prepare you charter, and you plan to present it to your Steering Committee on Friday. You are managing a software project, and the business need stated that you should use agile for the first time in our
company rather than waterfall. In the Develop Project Charter process, this is then______________


A.
Tool and technique
B. Part of the enterprise environment factors as an input to this process
C. A high-level requirement
D. Stated in the strategic plan as a tool and technique in this process

Correct Answer: C

Explanation:

Explanation:
The project charter formally authorizes the existence of the project and provides the project manager with the organizational resources for the project activities. Using agile is an example of a high-level requirement, which also is included in the charter.