Project Management Professional (PMP) Exam Practice – Question1843

You completed your stakeholder analysis. How do you want to manage those stakeholders that have a high interest in your project and high power over decisions affecting your project?


A.
Manage them closely
B. Keep them satisfied
C. Keep them informed
D. Monitor them occasionally

Correct Answer: A

Explanation:

Explanation:
You must manage them closely. High-power/high-interest stakeholders who do not support your project could have a devastating effect on your project.