Project Management Professional (PMP) Exam Practice – Question1844

Change requests include a group of potential changes to a project. Types of change requests include all the following EXCEPT______________


A.
Defect repairs
B. Maintenance requests
C. Corrective actions
D. Preventive actions

Correct Answer: B

Explanation:

Explanation:
Defect repairs, corrective actions, and preventive actions are types of change requests that occur on a project. Maintenance requests typically would be outside the scope of the project itself.