You are working on a project that needs approval from your City Council and the courts, because the project is one with significant environmental and social impacts. Although many consumer groups are advocates of this project, others are opposed to it.
Hearings are scheduled to resolve these issues and to obtain the needed permits to proceed. In preparing your human resource plan, you decide to designate a person as the court liaison, which is an example of a______________
A. Role
B. Responsibility
C. Required competency
D. Ability of the team member to make appropriate decisions
Hearings are scheduled to resolve these issues and to obtain the needed permits to proceed. In preparing your human resource plan, you decide to designate a person as the court liaison, which is an example of a______________
A. Role
B. Responsibility
C. Required competency
D. Ability of the team member to make appropriate decisions