Project Management Professional (PMP) Exam Practice – Question1848

Based on a recent quality audit of your project, your organization's quality assurance department is supportive of your approach as it notes the following characteristics of quality that are being followed consistency. They include all of the follow
EXCEPT______________


A.
Cost of quality
B. Customer satisfaction
C. Management responsibility
D. High-performing team

Correct Answer: D

Explanation:

Explanation:
This high-performing team is covered in develop project team and obviously is important and necessary. However, regarding quality management other key concepts are prevention over inspection and continuous improvement.