Project Management Professional (PMP) Exam Practice – Question1850

You are managing a major international project that involves multiple performing organizations.
To establish the guiding rules for the project regarding quality, you and your project team must develop a______________


A.
Improvement management plan
B. Configuration management plan
C. Quality policy
D. List of quality metrics for the project

Correct Answer: C

Explanation:

Explanation:
The quality policy includes the overall intentions and the direction of the organization regarding quality and as formally expressed by top management. When the performing organization lacks a formal quality policy or when the project involves multiple performing
organizations, as in a joint venture, the project management team must develop a quality policy for the project as an input to its quality planning.
PMI, PMBOK Guide, 2013, 234