Project Management Professional (PMP) Exam Practice – Question1854

Assume you are preparing your procurement management plan. A useful tool and technique is to______________


A.
Have a meeting
B. Use your risk register
C. Review the requirements document
D. Use your stakeholder register

Correct Answer: A

Explanation:

Explanation:
Meetings are another tool and technique in plan procurement management. They are held as research alone may not provide specific information for a procurement strategy without additional information exchange with potential bidders. Through collaborating
with potential bidders the organization purchasing the material or service may benefit. Suppliers may benefit to influence a mutually beneficial approach or product.