Project Management Professional (PMP) Exam Practice – Question1856

In order for a matrix organizational approach to be successful, the two-boss situation should be resolved. To overcome the two-boss problem, it is important to______________


A.
Have the project manager and the functional manager work together to complete performance evaluations
B. Prepare a responsibility chart to define responsibilities
C. Guarantee a balance of power between the functional manager and the project manager
D. Promote interface relationship management

Correct Answer: A

Explanation:

Explanation:
In a matrix environment, project team members have two bosses: the project manager and their functional line manager. People often are unclear as to which manager is their “real” boss, as there may be a continual shifting balance of power. To avoid confusion
regarding performance issues, it is a best practice to have the project manager and functional line manager complete the individual’s performance evaluations. Also, greater weight should be given to the project manager’s assessment for the time the individual
actually worked on the project.