Project Management Professional (PMP) Exam Practice – Question1857

The resource calendar is an output of which following process?


A.
Develop project team
B. Acquire project team
C. Estimate activity durations
D. Manage project team

Correct Answer: B

Explanation:

Explanation:
The resource calendar is an output from the acquire project team process. Other outputs are project staff assignments and updates to the project management plan, especially the human resource management plan. A resource calendar is also an output of the
develop human resource plan process as part of the staffing management plan and the conduct procurements process.