Project Management Professional (PMP) Exam Practice – Question1858

An intentional activity to ensure future performance of project work is aligned with the project management plan is______________


A.
Preventive action
B. Corrective action
C. Implemented change requests
D. Work performance information

Correct Answer: A

Explanation:

Explanation:
As a specific subset of change requests, approved preventive actions are an input to the direct and manage project work process. Such actions are intentional to ensure the future performance of the project work is aligned with the project management plan.