Project Management Professional (PMP) Exam Practice – Question1859

Close procurements is a process that involves includes activities for administrative closure such as______________


A.
Customer acceptance and final payment
B. Audit project success or failure and archiving records
C. Final contractor payment and lessons learned
D. Transition of the final product and acceptance of deliverables

Correct Answer: B

Explanation:

Explanation:
Administrative closure includes step-by-step methodologies that address: actions and activities necessary to satisfy completion or exit criteria for the phase or the project; actions or activities to transfer the products, services, or results to the next phase or to
production or operations; and activities to collect project or phase records, audit success or failure, gather lessons learned, and archive information for future use in the organization.