Project Management Professional (PMP) Exam Practice – Question1861

Assume you are managing a project, and your project management plan has been approved. Your project has a high level of change associated with it. There is active and ongoing stakeholder involvement. This means you probably are working with a(n)


A.
Adaptive life cycle
B. Iterative life cycle
C. Incremental life cycle
D. Predictive life cycle

Correct Answer: A

Explanation:

Explanation:
The adaptive life cycle is one that is known as change driven or one with agile methods and is set up to respond to change and ongoing stakeholder involvement. This approach differs from iterative and incremental as durations are very rapid and are fixed in time
and cost. This approach is preferred in a rapidly changing environment where requirements and scope are difficult to define in advance and when it is possible to define small incremental improvements, which deliver value to stakeholders.