Project Management Professional (PMP) Exam Practice – Question1863

You are conducting a stakeholder analysis on your project. After identifying potential stakeholders, the next step in the process is to______________


A.
Determine their desired level of participation
B. Provide detailed contact information for each identified stakeholder
C. Perform an assessment to see how each stakeholder might react in certain situations
D. Analyze each stakeholder's impact or support and classify them

Correct Answer: D

Explanation:

Explanation:
The second step in the stakeholder analysis process is to analyze the potential impact or support each stakeholder could generate and then to classify the stakeholders to define an approach or strategy.