You are conducting a stakeholder analysis on your project. Your organization uses an approach to classify stakeholders based on their level of authority and their active involvement in the project.
This approach is known as______________


A.
A power/interest grid
B. A power/influence grid

C. An influence/impact grid
D. A salience model

Correct Answer: B

Explanation:

Explanation:
Although a number of classification models are available to help prioritize the key stakeholders, the power/influence grid groups stakeholders based on their level of authority or power and their active involvement or interest in the project.