When managing projects, one important technique is capturing lessons learned from previous projects to improve the organization's project management process. Therefore, in planning the project, it is important to plan the closing procedures, particularly to
review the______________
A. Risk responses that were used
B. Checklists for risk identification
C. WBS and scope documents
D. Team members' performance feedback
review the______________
A. Risk responses that were used
B. Checklists for risk identification
C. WBS and scope documents
D. Team members' performance feedback