Project Management Professional (PMP) Exam Practice – Question1869

During a bidders conference, it is important that______________


A.
Only qualified sellers participate
B. All potential sellers are given equal standing
C. The evaluation criteria for the proposal is used to determine participation
D. Responses to questions be provided solely to the prospective seller that asked the question

Correct Answer: B

Explanation:

Explanation:
Bidders conferences are conducted to ensure all prospective sellers have a clear and common understanding of the requirements. They are not used to prequalify vendors. Thus, all vendors are treated equally.