Project Management Professional (PMP) Exam Practice – Question1872

All the following are processes in project procurement management EXCEPT______________


A.
Terminate procurements
B. Control procurements
C. Plan procurement management
D. Close procurements

Correct Answer: A

Explanation:

Explanation:
Termination is a word used to define a contract ending through mutual agreement by both parties, the default of one party, or for the convenience of the buyer. PMI, PMBOK Guide, 2013, 355, 387