Project Management Professional (PMP) Exam Practice – Question1878

One way to make it more likely practice project risk management on projects is to______________


A.
Hold meetings
B. Have the team take an orientation class on risk management early in the project
C. Give one team member the responsibility for risk management working in conjunction with the PMO
D. Assign each team member a risk to own, which is documented in the risk register

Correct Answer: A

Explanation:

Explanation:
Meetings are a tool and technique in the control risks process. Risk management should be an agenda item at periodic status meetings. While the amount of time needed for risk management will vary depending on the identified risks, their priority, and the