Project Management Professional (PMP) Exam Practice – Question1880

Work performance information in control risks means that______________


A.
Recommended preventive or corrective action is considered through change requests
B. Outcomes of risk reassessments and risk audits are documented
C. Templates to the risk management plan and the risk register are recommended
D. A mechanism to communicate and support project decision making is provided

Correct Answer: D

Explanation:

Explanation:
All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision making.