Project Management Professional (PMP) Exam Practice – Question1882

For complex procurement items, often contract negotiation can be an independent process. An example of an input if such a process is used is______________


A.
Open items list
B. Approved changes
C. Documented decisions
D. Expert judgment

Correct Answer: A

Explanation:

Explanation:
Issues or an open item list are examples of inputs if contract negotiation is an independent process. Outputs are documented decisions. While contract negotiations may need to be a separate process for complex procurements, for simple procurement items, the
terms and conditions of the contract can be fixed and nonnegotiable.