Project Management Professional (PMP) Exam Practice – Question1884

Each project can benefit from stakeholder involvement; however, it is in both the project manager's and the teams' best interest to ensure that all project stakeholders have positive attitudes toward the project and its goals and objectives. Working as a project
manager, you have a number of key stakeholders on your project. The stakeholder that identifies potential conflicts between organizational strategies and project goals is the______________


A.
Chairperson of the Governance Board
B. Program manager
C. Director of the project management office
D. Chief Operating Officer

Correct Answer: B

Explanation:

Explanation:
Organizational strategy provides guidance and direction to project management. Portfolio managers, sponsors, or program managers identify alignment or potential conflicts between organizational strategies and project goals and communicates them to the
project manager.