Project Management Professional (PMP) Exam Practice – Question1888

Assume you are working on a multi-phase project as your project is planned to last three years. A best practice is to______________


A.
Periodically review the business case
B. Use a single prime contractor and have this contractor award any subcontracts
C. Rely on your PMO for guidance
D. Set up a `tight matrix'

Correct Answer: A

Explanation:

Explanation:
The business case is an input to the develop project charter process. On a multi-phase project, it should be reviewed periodically to ensure the project is on track to deliver the business benefits.