Project Management Professional (PMP) Exam Practice – Question1889

On a large medical billing system project, the team is large and communication has been quite a challenge to control. The Project Expeditor has been used to help with this problem. What is one of the main differences between the Project Expeditor and Project
Coordinator?


A.
the Project Expeditor is another title for the Project Manager

B. the Project Expeditor is another title for Project Coordinator
C. the Project Expeditor has limited or no decision-making ability
D. the Project Expeditor has decision-making ability

Correct Answer: C