The data warehouse project is about halfway complete at a major retail client.
Your company is doing the implementation and has twelve team members in various locations across three different buildings. Communication and team-building has been a real challenge. Which of the following would fix or improve this problem?
A. Changing the organization to a functional structure
B. Co-location
C. Replacing the Project Manager
D. Hiring Project Coordinators