Project Management Professional (PMP) Exam Practice – Question1896 What is the main output of Monitoring and Controlling? A. Charter B. Controlling stakeholders C. Corrective action D. Project product Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question1895Project Management Professional (PMP) Exam Practice – Question1897