You are the Project Manager on a cellular bluetooth amplifier project and are in the Planning phase. During a team meeting, a Functional Manager attempts to validate if the project meets company goals. The Functional Manager will report this finding back to
senior management to determine if the project should continue, be modified or be canceled. What is this process called?


A.
Delphi Technique
B. Management by objectives (MBO).
C. Return on investment
D. Management product analysis

Correct Answer: B