Project Management Professional (PMP) Exam Practice – Question1902

On a wireless internet access project, the team is large with 40 people, and controlling communication has been a challenging for the team to make progress. The Project Coordinator has been used to help with this problem. What is one of the main differences
between the Project Coordinator and the Project Expeditor?


A.
The Project Expeditor is another title for the Project Manager
B. The Project Coordinator has decision-making ability
C. The Project Expeditor is another title for Project Coordinator
D. The Project Expeditor has decision-making ability

Correct Answer: B