Project Management Professional (PMP) Exam Practice – Question1906

A Project Manager has completed the Scope Definition process. The customer and sponsor have shortened the schedule by four weeks and decided that the work breakdown structure will be excluded. What would be the best action the Project Manager should
take?


A.
Begin execution of the project
B. Provide the customer and sponsor an updated schedule and budget
C. Call a meeting and notify the team of the change in schedule
D. Discuss with the customer and sponsor the ramifications of excluding the WBS

Correct Answer: D