Project Management Professional (PMP) Exam Practice – Question1909

The e-commerce project has gone well other than the fact that the sponsor changed three
different times. The project is in closure. All of the following would be created in closing except?


A.
Lessons learned
B. Release of resources
C. Contract audit
D. Project archives

Correct Answer: C