Project Management Professional (PMP) Exam Practice – Question1913 Which of the following is an output of a change control system? A. Change requests B. Approved changes C. Impact analysis D. Signoff Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1912Project Management Professional (PMP) Exam Practice – Question1914