Project Management Professional (PMP) Exam Practice – Question1919

You are the Project Manager for a high speed data communications project. You have just finished putting together all the various plans into an integrated document. Which of the following will you do next?


A.
Develop Project Management Plan
B. Integrated Change Control
C. Direct and Manage Project Execution
D. Charter Signoff

Correct Answer: C