Project Management Professional (PMP) Exam Practice – Question1923

The customer has requested a five-week delay on the project while they rebuild a warehouse used for manufacturing a key piece of the project. This delay wasn't planned, but the project couldn't continue without it. The company is limited on available resources.
This delay will be best shown in what?


A.
Responsibility assignment matrix
B. Network diagram
C. Budget
D. Work breakdown structure (WBS).

Correct Answer: B