Project Management Professional (PMP) Exam Practice – Question1924 Which of the following would a team create as a result of using a change control system? A. Change requests B. Approved changes C. Impact analysis D. Signoff Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1923Project Management Professional (PMP) Exam Practice – Question1925